Nationwide Children’s Hospital RB3
225,000 sq ft Research Building
Description:
Sauer provided the following preconstruction services:
- Attended design development meetings
- Provided design concept input
- Developed multiple budgets
- Developed GMP Pricing
- Provided Value Engineering
- Provided Constructability Reviews
- Provided Life Cycle Cost Input
Owner:
Nationwide Children’s Hospital
Location:
Columbus, Ohio
Architect:
NBBJ
Construction Manager:
Turner Construction Company
Mechanical Engineer:
HAWA Engineering
Systems Installed:
6 – Multi-level Custom Air Handling Units
2 – Steam Boilers
4 – Hot Water Boilers
- Pumps, Heat Exchangers, tanks, etc
- 45,000 linear feet of piping, including heating hot water, chilled water, condenser water, and steam and condensate
- DDC Controls